Remove all splits

  1. Find the bar representing the task in the Gantt chart.
  2. Move the mouse cursor onto the bar and click the right mouse button.
  3. Select the Remove All Splits option from the context menu.
  4. The splits for the task is removed and the task scheduled in one continuous duration.

or

  1. Select a block of tasks in the spreadsheet.
  2. Move the mouse cursor onto the bar and click the right mouse button.
  3. Select the Remove All Splits option from the context menu.
  4. The splits for all selected tasks is removed and each task scheduled in one continuous duration.

Note When the percentage complete is set on a task, it is automatically split into the completed and remaining sections. You cannot remove this automatic split unless you set the percentage complete to 0 or 100.